Thinking of Building a Data Center?
I read a thread a while back on a forum from an OP who wondered how much it would cost to build his own data center. A lot of variables come into play determining those costs. Certainly, just gaining approval to build a data center is one of those variables. How much expertise does your staff possess in the area of conceptualizing design and build-out? Is there a hard and fast template for architects? Are the people who are going to manage the new data center the same as those who will be building it? I’d heard it said that building a data center is a once in a lifetime undertaking. I suspect that’s generally true across the board.
How do you know what to ask or who to turn to for guidance?
How far out should you plan? When you figure that most data centers end-of-life cycle is 15-20 years, should you build out to year seven and continue building out as you grow? Or do you build out to year 15 to begin? Unfortunately, that question is normally answered by the amount of funding available.
Tier Level?
Most data centers are generally defined by their Tier Level, so much of the estimation of funds is directly tied to which Tier Level to build out to. Tier 4 data centers will cost significantly more than Tier 1 data centers. Tier 1 is the lowest rated Tier and is prone to downtime - and Tier 4 is the most robust, redundant, and functional.
Tier I: A single path for power and cooling distribution, without redundant components, providing 99.671% availability
Tier II: A single path for power and cooling distribution, with redundant components, providing 99.741% availability
Tier III: Multiple active power and cooling distribution paths but only one path active, redundant components, concurrently maintainable, providing 99.982% availability
Tier IV: Multiple active power and cooling distribution paths, redundant components, fault-tolerant, providing 99.995% availability
Energy Costs?
Consider how far we’ve come in the last 5 years with regard to energy footprints. How can anyone possibly predict the state of this industry in another 15 years? Thus, energy needs to be scalable. Will our racks become more dense? Will new processors and RAM modules consume massive energy, or just the opposite? What is today’s trend, and what looms on the horizon? Part of your business plan must be trend analysis.
Green Technologies?
What is Green? Does Green relate to carbon footprints? Would it pay to design Green, both in energy savings and marketability? A recent Google search for Green Data Centers turned up 288,000,000 results. Some green data centers are powered entirely through renewable wind energy - and designed to operate at approximately 60% lower energy utilization per square foot than comparable data centers of the same size. This translates directly into more computing power using less energy in a given building.
Who will actually build the data center?
Determining the engineering firm, construction company, their sub-contractors, etc. and working through the build out is a monumental undertaking. Murphy’s Law still prevails. What can go wrong, will go wrong.
Millions of dollars are at risk
A couple of years ago, a study determined the cost to build a 150,000 square foot data center with 150 employees averaged from $16-$17 million on the low end to $19-$22 million on the high end. The most expensive were obviously on the East and West coasts. The Midwest and Southeast came in on the low end.
I read a thread a while back on a forum from an OP who wondered how much it would cost to build his own data center. A lot of variables come into play determining those costs. Certainly, just gaining approval to build a data center is one of those variables. How much expertise does your staff possess in the area of conceptualizing design and build-out? Is there a hard and fast template for architects? Are the people who are going to manage the new data center the same as those who will be building it? I’d heard it said that building a data center is a once in a lifetime undertaking. I suspect that’s generally true across the board.
How do you know what to ask or who to turn to for guidance?
How far out should you plan? When you figure that most data centers end-of-life cycle is 15-20 years, should you build out to year seven and continue building out as you grow? Or do you build out to year 15 to begin? Unfortunately, that question is normally answered by the amount of funding available.
Tier Level?
Most data centers are generally defined by their Tier Level, so much of the estimation of funds is directly tied to which Tier Level to build out to. Tier 4 data centers will cost significantly more than Tier 1 data centers. Tier 1 is the lowest rated Tier and is prone to downtime - and Tier 4 is the most robust, redundant, and functional.
Tier I: A single path for power and cooling distribution, without redundant components, providing 99.671% availability
Tier II: A single path for power and cooling distribution, with redundant components, providing 99.741% availability
Tier III: Multiple active power and cooling distribution paths but only one path active, redundant components, concurrently maintainable, providing 99.982% availability
Tier IV: Multiple active power and cooling distribution paths, redundant components, fault-tolerant, providing 99.995% availability
Energy Costs?
Consider how far we’ve come in the last 5 years with regard to energy footprints. How can anyone possibly predict the state of this industry in another 15 years? Thus, energy needs to be scalable. Will our racks become more dense? Will new processors and RAM modules consume massive energy, or just the opposite? What is today’s trend, and what looms on the horizon? Part of your business plan must be trend analysis.
Green Technologies?
What is Green? Does Green relate to carbon footprints? Would it pay to design Green, both in energy savings and marketability? A recent Google search for Green Data Centers turned up 288,000,000 results. Some green data centers are powered entirely through renewable wind energy - and designed to operate at approximately 60% lower energy utilization per square foot than comparable data centers of the same size. This translates directly into more computing power using less energy in a given building.
Who will actually build the data center?
Determining the engineering firm, construction company, their sub-contractors, etc. and working through the build out is a monumental undertaking. Murphy’s Law still prevails. What can go wrong, will go wrong.
Millions of dollars are at risk
A couple of years ago, a study determined the cost to build a 150,000 square foot data center with 150 employees averaged from $16-$17 million on the low end to $19-$22 million on the high end. The most expensive were obviously on the East and West coasts. The Midwest and Southeast came in on the low end.