Lambda says it has built the first large-scale network that uses co-packaged optics, and the site is a data center in Quebec. It uses Nvidia Photonics switches to link racks of GB300 NVL72 systems holding more than 10,000 GPUs. The claim of “first” comes from Lambda, so treat it as the company’s own description.
Start with the problem the technology solves. Ordinary switches use pluggable optical modules at the front panel, and signals travel as electricity across the switch before turning into light. Co-packaged optics place the optical engines right beside the switch chip. That cuts the electrical path from inches to millimeters, which saves power and removes one point of failure.
Gains are real but modest in the numbers shared. Tests found network latency fell by about four percent at rack scale and up to ten percent across a pod. Nvidia adds that its photonics cut network power and raise reliability by up to 15 times. Those are vendor claims, and independent results will say more over time. Each switch offers 144 ports at 800Gbps. They are liquid-cooled, and the optics run at about 36°C, compared with 51°C for pluggable parts, which should reduce heat stress.
Why does a small latency change matter? Gilad Shainer of Nvidia explains that in an AI factory, every interruption stalls a training job, and every watt counts. When thousands of GPUs wait for each other, a few percent of network delay turns into expensive idle time. Lambda’s Dave Ward calls the deployment an important step toward infrastructure for the next generation of AI.
The location surprises some readers. Lambda lists data centers across the US, Europe and Asia-Pacific, but Canada doesn’t appear in its public cloud documents. QScale, which hosts the equipment, confirmed its role in a LinkedIn post and called the build a Quebec achievement. Its campus offers 142MW, runs on almost entirely renewable power and uses free cooling for up to 80 percent of the year. A further 60MW data center is under construction, and Goldman Sachs Alternatives owns the company through an infrastructure portfolio.
Open questions remain. Neither company has said when customers can rent capacity from this site, or whether it will join Lambda’s public cloud. Buyers should wait for those details before assuming the gains reach them.